Thursday, August 20, 2009

My Stomach Keeps Making Noises In Bed

It is!

The last 3 days, a lot has happened:
Tuesday morning at 6:00 clock we came to the site, the construction group was already there, waiting for the crane! The good with ner-five minutes late then drove up shortly after the seventh Since our road is very close was not all that easy!
But despite initial difficulties, the first wall stood at 8! After that, everything ran like clockwork! About 2 hours later was the ground floor!
At noon came the attic turn! Of course, many viewers were
site!
The men have the first Days all the work done and had earned her a beer after honest!
Wednesday was then covered the roof and mount the solar system and continued to work inside! Since it was really warm solangsam they have done to me because on the roof a bit sorry! Our One electric
has already started in the living room to draw lines, then it is also using the device of the outlets have noticed that the staircase is wrong! Instead left it starts to the right! But it fits! Must now look like the time goes on!
Today was then the chief engineer said there, or rather because of our representation is on vacation! He is
everything went through with us and make a note of everything. Also has times directly on the phone because of the stairs, must now wait times at which rumkommt! All in all, we are quite satisfied! Thanks again to the troop build! Have done great work!

0 comments:

Post a Comment