Thursday, August 6, 2009

Designer Gowns For Rent In Makati

house building is coming soon!

So yesterday we have met our supervisor Mr. G.! He has removed the bottom plate and was satisfied, then we of course!
Now, the house construction are no more obstacles! On Monday will also finally learn what day it is!

Thursday, July 23, 2009

Aquaphor Baby Wash Eczema

bottom plate

The last 2 weeks, much has happened on the site, the foundation for the floor slab was completed yesterday and this was then finally completed! Partnerbau has done a good job! Thank you!
pictures to follow!

Monday, June 22, 2009

Cervix Pentration Imgages

earthworks







As slow motion comes into play with us!
weekend we have pushed the topsoil on site.
good that our father / father-in-itself in the civil engineering works, we can save a lot!
was dredged At 8:00 clock to 12 clock! Now we wait until Tuesday because the construction manager come from Partnerbau besrpricht and the next steps with us!
bottom plate is planned for the 30KW!
house up 34kW!
pictures follow!